Leading With Data· a Bicycle Guide
Guide highlights

Higher plant availability, output, and quality with fewer, better-utilized people. Predictable, planned, scheduled work replacing chaotic firefighting.

  • Evaluate your current maintenance practices honestly using the Maintenance Fitness Questionnaire.
  • Fix the core processes: work identification, work orders, planning, scheduling, and CMMS.
  • Select deterioration strategies (PM, PdM, RCM, PMO, TPM, bust-and-fix) that fit each asset's consequences and life cycle.

Book profile

Managing Factory Maintenance

One book, placed in its field — what Joel Levitt's book gets right, where it goes further than the rest, and what the rest of the field adds.

Edited by Mike West

Choose a reading path or an exercise

Suggested sections

Choose a starting point below. Each link opens a section of this guide.

Do this now — Top Management Support and Constancy of Purpose

  1. Write down the downtime hours per month that production has agreed to release for planned maintenance, and have the plant manager sign it.
  2. Ring-fence the training and condition-monitoring budget so it cannot be moved to cover overtime or spare-parts overruns.
  3. Add maintenance leading indicators (PM compliance, planned-work percentage) to the executive review next to output and cost.

Then continue in Top Management Support and Constancy of Purpose.

Edition 1·Updated 2026-10-03·24 min read

Sources

About this book

An overview of the book, with source information for further reading.

A practical field guide to transforming a reactive maintenance department into a proactive, world-class function that boosts plant output, reduces costs, and eventually shrinks the need for maintenance itself.

More on this book

Managing Factory Maintenance argues that in an era of globalized production and mass retirement of skilled workers, a factory's survival hinges on how well it manages its maintenance function. Joel Levitt, drawing on decades of teaching thousands of maintenance professionals worldwide, reframes maintenance from a 'necessary evil' cost center into a strategic asset that increases plant availability, quality, and competitiveness. The book walks the reader through evaluating current practices, building sound maintenance processes (work orders, planning, scheduling, CMMS), choosing the right deterioration strategy (PM, PdM, RCM, PMO, TPM), and integrating maintenance with production, purchasing, stores, and accounting. It combines hard tools—benchmarks, budgets, task lists, formulas—with the softer disciplines of training, supervision, communication, and time management, giving supervisors and managers a coherent story and a reference they can consult for almost any maintenance question.

Movement I

Orient

In this part

What this book claims, and who wrote it.

  • — The book's one-line promise
  • — The author and where the book stands

A practical field guide to transforming a reactive maintenance department into a proactive, world-class function that boosts plant output, reduces costs, and eventually shrinks the need for maintenance itself.

The need-to-know

The real payoff is increasing overall equipment effectiveness (OEE) and plant output, not merely reducing maintenance cost. Continuous improvement requires commitment, measurement, information, investigation, and action; it is everyone's job. Good information—centered on the work order—is the foundation of all analysis, decision-making, and improvement.

About this guide

The guide describes these challenges, steps and possible outcomes.

Who it is for

A maintenance manager or supervisor responsible for keeping a factory running who wants to keep the plant competitive, avoid outsourcing/closure, and be respected as a strategic contributor.

Challenges

  • In practice · Aging equipment, retiring skilled workers, downsized crews, and low-cost global competitors threaten the plant with either slow deterioration or sudden outsourcing.
  • For the reader · The reader feels overwhelmed in a pressure cooker of emergencies, undervalued as a 'grease monkey' or necessary evil, and unsure how to prove maintenance's worth.

Steps to consider

  1. 1Evaluate your current maintenance practices honestly using the Maintenance Fitness Questionnaire.
  2. 2Fix the core processes: work identification, work orders, planning, scheduling, and CMMS.
  3. 3Select deterioration strategies (PM, PdM, RCM, PMO, TPM, bust-and-fix) that fit each asset's consequences and life cycle.
  4. 4Integrate maintenance with production, purchasing, stores, and accounting, and build a zero-based budget.
  5. 5Invest in people through training, cross-training, supervision, communication, and time management.

Risks

Continued deterioration eroding market share (slow death) or sudden plant closure via outsourcing (quick death). Loss of irreplaceable knowledge as old-timers retire without capture.

Intended result

Higher plant availability, output, and quality with fewer, better-utilized people. Predictable, planned, scheduled work replacing chaotic firefighting.

Set the record straight

What this book sets straight

The common beliefs this book pushes back on.

The myth

Maintenance is a necessary evil and pure expense to be minimized.

The reality

Well-run maintenance is a strategic asset that enhances the whole organization's competitiveness by increasing output, quality, and reliability.

The myth

Having PM, TPM, RCM, or PMO in place means you are doing maintenance management.

The reality

Those initials are only process aids; the underlying maintenance processes must be whole and complete for the aids to help.

The myth

Maintenance problems are technical problems solved by new tools, gadgets, and computers.

The reality

Almost all maintenance difficulties are really people problems—attitudes, training, systems, and communication—masquerading as maintenance problems.

The myth

Cutting PM saves money because breakdowns don't immediately rise.

The reality

Deterioration has a tail; cutting PM only looks good until the failure curve decays, and the piper always gets paid 1-2 years later.

The myth

The best mechanic is the best PM inspector.

The reality

PM requires proactive, disciplined, curious diagnosticians who follow lists faithfully—a different profile than a reactive 'fixer.'

Movement II

Map

The book's main ideas and how they connect.

In this part

Managing Factory Maintenance's own model — and how it sits inside its field.

  • — 12 constructs the book works with
  • — Where it agrees with the field, exceeds it, or fills a gap
The Conditions1· the context you inherit
Top Management Support and Constancy of Purpose
What You Design4· the levers you pull
Proactive Maintenance Strategy SelectionTraining, Cross-Training, and Skill LevelPlanning and Scheduling DisciplineMaintenance Information Quality (Work Order/CMMS Integrity)
What It Produces2· the states it creates
Proactive Discipline and AttitudeWorker/Operator Ownership and Motivation
What You Do1· the behaviours that follow
Maintenance Process Quality

The constructs

Top Management Support and Constancy of Purpose

The degree to which senior leaders understand, appreciate, fund, and provide long-term commitment (including downtime and resources) to the maintenance effort rather than short-term cost cutting.

Proactive Maintenance Strategy Selection

The extent to which the department deploys strategy fitted to consequences and life cycle—PM, predictive maintenance, RCM, PMO, TPM—rather than reactive bust-and-fix, targeting the most dangerous, expensive, or common failure modes.

Planning and Scheduling Discipline

The maturity of distinct planning (resource identification, estimating, job packages) and scheduling (coordination with production, weekly schedules, backlog management) practices that converge people, parts, tools, and assets on time.

Maintenance Information Quality (Work Order/CMMS Integrity)

The completeness, accuracy, and consistency of data captured through work orders and the CMMS, forming the unique history used for analysis, benchmarking, and decision-making.

Training, Cross-Training, and Skill Level

The investment in continual craft, multi-craft, and management training that closes the gap between modern equipment technology and workforce skills, targeting 1-5% of direct hours.

Proactive Discipline and Attitude

The self-disciplined, proactive mindset and constancy with which inspectors and mechanics perform tasks without close supervision, act before failure, and pursue root causes rather than firefighting.

Worker/Operator Ownership and Motivation

The sense of ownership, pride, and responsibility operators and mechanics feel for their equipment, cultivated through TPM, cross-training, and freedom from fear, driving self-motivation.

Maintenance Process Quality

The degree to which maintenance is delivered through robust processes (right job, right asset, right way, right materials) that produce good service without depending on individual heroism, minimizing rework and iatrogenic failures.

Equipment Reliability (MTBF)the outcome

The reliability of assets expressed as extended mean time between failures and reduced number and severity of breakdowns achieved through effective maintenance strategy and execution.

Plant Availability and Output (OEE)

Overall equipment effectiveness and effective productive output of the plant—availability, performance efficiency, and quality rate—reflecting reduced downtime, speed losses, and defects.

Total Cost of Maintenance

The overall long-term cost of maintenance including labor, materials, downtime, and ownership, which is minimized at a balanced level of PM activity (too little causes breakdowns, too much wastes resources).

Organizational Competitiveness and Survival

The ultimate business outcome in which lower unit cost, higher availability, and quality enhance the organization's competitive position and survival against low-cost and innovative competitors.

How they connect (18)
  • Top Management Support and Constancy of Purpose → predicts → Proactive Maintenance Strategy Selection
  • Top Management Support and Constancy of Purpose → predicts → Training, Cross-Training, and Skill Level
  • Proactive Maintenance Strategy Selection → influences → Proactive Discipline and Attitude
  • Proactive Maintenance Strategy Selection → predicts → Equipment Reliability (MTBF)
  • Planning and Scheduling Discipline → predicts → Maintenance Process Quality
  • Planning and Scheduling Discipline → influences → Total Cost of Maintenance
  • Maintenance Information Quality (Work Order/CMMS Integrity) → predicts → Maintenance Process Quality
  • Maintenance Information Quality (Work Order/CMMS Integrity) → influences → Equipment Reliability (MTBF)
  • Training, Cross-Training, and Skill Level → predicts → Maintenance Process Quality
  • Training, Cross-Training, and Skill Level → influences → Worker/Operator Ownership and Motivation
  • Worker/Operator Ownership and Motivation → predicts → Maintenance Process Quality
  • Proactive Discipline and Attitude → mediates → Equipment Reliability (MTBF)
  • Maintenance Process Quality → predicts → Equipment Reliability (MTBF)
  • Equipment Reliability (MTBF) → predicts → Plant Availability and Output (OEE)
  • Equipment Reliability (MTBF) → influences → Total Cost of Maintenance
  • Plant Availability and Output (OEE) → predicts → Organizational Competitiveness and Survival
  • Total Cost of Maintenance → influences → Organizational Competitiveness and Survival
  • Top Management Support and Constancy of Purpose → moderates → Proactive Discipline and Attitude

Where this book diverges from the corpus

  • lags The book covers consequence- and life-cycle-based strategy choice (PM, PdM, RCM, PMO, TPM), but the field adds a documented strategy tied top-down to corporate goals and separates out PM/PdM and RCM as distinct constructs.
  • lags The book describes planning and scheduling practices well, but the field goes further with dedicated planners separated from crews and a separate construct on planner selection, staffing and training.
  • exceeds The book adds a concrete investment target of 1-5% of direct hours and a focus on closing the gap between equipment technology and workforce skills, which the field states more generally.

Movement III

Master

Explore the book's ideas, examples and practical tools.

In this part

How the author makes the case — section by section, with the book's own tools.

  • — 12 sections, in the book's order
  • — The book's frameworks, checklists, and worked cases
Proactive Discipline and Attitude
strong · 1 source
  • Managing Factory Maintenance
In this section

This section covers the mindset in which inspectors and mechanics complete routine tasks reliably without supervision, act before failure, and chase root causes. It shows how to build it and what undermines it.

Proactive Discipline and Attitude

The self-disciplined, proactive mindset and constancy with which inspectors and mechanics perform tasks without close supervision, act before failure, and pursue root causes rather than firefighting.

Why it matters. Even a well-designed strategy fails to improve reliability if inspections are skipped or signs of wear are ignored, because the benefit lies in consistent execution.

Myth

Proactive attitude is a personality trait you hire for, so it cannot be developed in a reactive workforce.

Reality

Behavior follows what the system rewards. When the plant praises heroic emergency repairs and ignores uneventful inspection rounds, people learn that firefighting pays, and a visible strategy plus consistent leadership shifts that quickly.

Tools for this
The least you need to know
  • Proactive behavior is shaped by what leaders reward and keep consistent, so it can be developed.
  • Root-cause follow-through on repeat failures is the clearest signal that discipline is real.
  • Visible, consistent leadership support turns a good strategy into daily practice.
Master this◆ Paid

The deep drill-down: 8 operational steps, a worked example from the source, 5 decision rules, 5 failure modes, and the “Proactive Discipline and Root Cause Log” tool. Included when you buy this guide.

The rest of this section

the full written section · 3 how-to steps · 2 pitfalls to watch for · 5 tools for this section. Included when you buy this guide.

Grounded in: Managing Factory Maintenance

Worker/Operator Ownership and Motivation
strong · 1 source
  • Managing Factory Maintenance
In this section

This section explains how operators and mechanics come to feel responsible for their equipment and how TPM, cross-training, and a fear-free environment build that. It treats ownership as a driver of self-motivation.

Worker/Operator Ownership and Motivation

The sense of ownership, pride, and responsibility operators and mechanics feel for their equipment, cultivated through TPM, cross-training, and freedom from fear, driving self-motivation.

Why it matters. People who feel ownership catch small abnormalities early and do careful work without being checked, while disengaged workers do the minimum and hide problems.

Myth

Ownership comes from incentives and accountability metrics such as bonuses tied to downtime.

Reality

Pay-for-metrics often push people to hide stoppages and misreport causes. Ownership grows when operators are trained to care for their machines, given authority to act on what they find, and not blamed for reporting problems.

Tools for this
The least you need to know
  • Ownership grows from skill, authority, and safety to speak up, not from bonuses.
  • Operator care tasks work only when training and time are provided with them.
  • Visible management response to reported abnormalities is what keeps reporting alive.
Master this◆ Paid

The deep drill-down: 8 operational steps, a worked example from the source, 5 decision rules, 5 failure modes, and the “Asset Ownership Handover Sheet” tool. Included when you buy this guide.

The rest of this section

the full written section · 3 how-to steps · 2 pitfalls to watch for · 3 tools for this section. Included when you buy this guide.

Grounded in: Managing Factory Maintenance

Maintenance Process Quality
strong · 1 source
  • Managing Factory Maintenance
In this section

This section describes how to deliver maintenance so that the right job is done on the right asset, the right way, with the right materials, regardless of who is on shift. It also covers reducing rework and failures caused by maintenance itself.

Maintenance Process Quality

The degree to which maintenance is delivered through robust processes (right job, right asset, right way, right materials) that produce good service without depending on individual heroism, minimizing rework and iatrogenic failures.

Why it matters. A fragile process that depends on a few skilled individuals produces uneven results and induced failures, so improvements fade when those people leave or are overloaded.

Myth

Good maintenance results come from having your best technicians, so process documentation is bureaucracy that slows them down.

Reality

Reliance on individual heroics is the symptom of a weak process: results vary by shift and collapse with turnover. Standard job plans, verification steps, and correct parts let average technicians produce consistent work and remove a major source of induced failures.

Tools for this
The least you need to know
  • A robust process delivers consistent results from average performers and does not rely on heroes.
  • Repeat failures soon after maintenance reveal process defects, not just individual errors.
  • Planning, data, skills, and ownership all feed process quality, so weakness in any one shows up here.
Master this◆ Paid

The deep drill-down: 7 operational steps, a worked example from the source, 5 decision rules, 5 failure modes, and the “Process-Before-Aid Readiness Sheet” tool. Included when you buy this guide.

The rest of this section

the full written section · 4 how-to steps · 2 pitfalls to watch for · 1 tool for this section. Included when you buy this guide.

Grounded in: Managing Factory Maintenance

Equipment Reliability (MTBF)
strong · 1 source
  • Managing Factory Maintenance
In this section

This section covers how to read and improve MTBF and the frequency and severity of breakdowns as the first outcome of the maintenance system. It points to which upstream levers move it.

Equipment Reliability (MTBF)

The reliability of assets expressed as extended mean time between failures and reduced number and severity of breakdowns achieved through effective maintenance strategy and execution.

Why it matters. Reliability is the point where maintenance effort turns into plant results, so a stalled MTBF reveals that upstream practices are not working before output and cost figures show it.

Myth

A rising MTBF proves the maintenance department is performing well.

Reality

MTBF can improve because of operating changes, product mix, or a bad year's outliers, and plant-wide averages hide poor performers among the strong. Read it asset by asset, with failure severity and cause, to see whether strategy and execution made the difference.

Tools for this
The least you need to know
  • Measure MTBF at the asset level; plant-wide averages conceal where reliability is actually failing.
  • Pair failure frequency with severity so you chase the failures that cost the most.
  • Treat reliability as a lagging signal of strategy, data, process, and discipline, and diagnose upstream when it stalls.
Master this◆ Paid

The deep drill-down: 8 operational steps, a worked example from the source, 5 decision rules, 5 failure modes, and the “Asset Reliability Curve Tracker” tool. Included when you buy this guide.

The rest of this section

the full written section · 4 how-to steps · 2 pitfalls to watch for · 1 tool for this section. Included when you buy this guide.

Grounded in: Managing Factory Maintenance

Plant Availability and Output (OEE)
strong · 1 source
  • Managing Factory Maintenance
In this section

This section explains how availability, performance, and quality combine in OEE and how reliability gains translate into productive output. It shows how to use OEE to find where capacity is lost.

Plant Availability and Output (OEE)

Overall equipment effectiveness and effective productive output of the plant—availability, performance efficiency, and quality rate—reflecting reduced downtime, speed losses, and defects.

Why it matters. OEE shows how much of the plant's capacity you convert into good product, so misreading it leads to investing in the wrong losses or in capacity you do not need.

Myth

OEE is mainly a maintenance metric, so improving it is the maintenance department's job alone.

Reality

Availability losses come from breakdowns, but performance and quality losses stem from changeovers, minor stops, material, and process settings that operations controls. Maintenance can drive availability, yet the full OEE gain needs a shared effort with production.

Tools for this
The least you need to know
  • Decompose OEE into its three factors to see which loss you are actually fighting.
  • Maintenance owns much of availability, but performance and quality need joint action with operations.
  • Focus OEE improvement on constraint equipment so gains become real output.
Master this◆ Paid

The deep drill-down: 8 operational steps, a worked example from the source, 5 decision rules, 5 failure modes, and the “OEE Loss Ledger (per machine or area)” tool. Included when you buy this guide.

The rest of this section

the full written section · 4 how-to steps · 2 pitfalls to watch for · 4 tools for this section. Included when you buy this guide.

Grounded in: Managing Factory Maintenance

Total Cost of Maintenance
strong · 1 source
  • Managing Factory Maintenance
In this section

This section frames maintenance cost as the sum of labor, materials, downtime, and ownership, and shows how to find the balance of PM activity that minimizes it. It also shows how planning and reliability reduce it.

Total Cost of Maintenance

The overall long-term cost of maintenance including labor, materials, downtime, and ownership, which is minimized at a balanced level of PM activity (too little causes breakdowns, too much wastes resources).

Why it matters. Judging maintenance by its budget line alone rewards cuts that raise downtime costs, while ignoring waste in over-maintenance, so the plant pays more in total.

Myth

Lowering the maintenance budget lowers the cost of maintenance.

Reality

Cutting spend usually shifts cost into breakdowns, expedited parts, and lost output that dwarf the savings. Total cost is lowest at a middle level of preventive activity: too little causes failures and too much consumes labor and parts needlessly.

Tools for this
The least you need to know
  • Total cost includes downtime and ownership, so a lower budget can mean higher cost.
  • Cost is minimized at a balanced PM level; both under- and over-maintenance raise it.
  • Planning discipline and reliability gains are the most dependable routes to lower total cost.
Master this◆ Paid

The deep drill-down: 8 operational steps, a worked example from the source, 5 decision rules, 5 failure modes, and the “PM Balance Cost Worksheet (per asset or asset class)” tool. Included when you buy this guide.

The rest of this section

the full written section · 4 how-to steps · 2 pitfalls to watch for · 3 tools for this section. Included when you buy this guide.

Grounded in: Managing Factory Maintenance

Organizational Competitiveness and Survival
strong · 1 source
  • Managing Factory Maintenance
In this section

This section connects maintenance results to the business outcome: unit cost, availability, and quality that decide whether the organization holds its position against low-cost and innovative rivals. It tells you how to carry that case to the executive level.

Organizational Competitiveness and Survival

The ultimate business outcome in which lower unit cost, higher availability, and quality enhance the organization's competitive position and survival against low-cost and innovative competitors.

Why it matters. If maintenance cannot show its effect on unit cost and delivery, it stays classified as overhead and loses funding just when competitors are closing the gap.

Myth

Competitiveness is decided by sales, pricing, and product innovation, and maintenance is too far downstream to matter.

Reality

Availability determines whether orders ship on time and unit cost determines how low you can price, and both depend directly on maintenance. A plant that cannot deliver reliably or hold cost loses to rivals regardless of how strong its product is.

Tools for this
The least you need to know
  • Maintenance reaches competitiveness through two paths: availability for delivery and total cost for pricing.
  • Executives fund what they see tied to unit cost and delivery, so translate maintenance results into those terms.
  • Benchmark against the strongest competitors, since survival depends on relative performance.
Master this◆ Paid

The deep drill-down: 8 operational steps, a worked example from the source, 5 decision rules, 5 failure modes, and the “Competitive Position Scorecard (maintenance to survival)” tool. Included when you buy this guide.

The rest of this section

the full written section · 3 how-to steps · 2 pitfalls to watch for · 4 tools for this section. Included when you buy this guide.

Grounded in: Managing Factory Maintenance

Top Management Support and Constancy of Purpose
strong · 1 source
  • Managing Factory Maintenance
In this section

This section shows what senior commitment to maintenance looks like in budgets, scheduled downtime, and tolerance for slow payback. It also shows how that commitment sets the ceiling for strategy, training, and shop-floor discipline.

Top Management Support and Constancy of Purpose

The degree to which senior leaders understand, appreciate, fund, and provide long-term commitment (including downtime and resources) to the maintenance effort rather than short-term cost cutting.

Why it matters. When leaders cut maintenance budgets to hit a quarterly number, they undermine strategy, skills, and discipline together, and the resulting breakdowns cost far more than the savings.

Myth

If the plant manager approves the annual maintenance budget and attends the kickoff, top management support is in place.

Reality

Support is measured when it costs something: whether leaders release a line for a planned PM window in a tight order month, or protect training hours during a shortfall. A reliability program that survives only in good quarters teaches the workforce to wait it out.

Tools for this
The least you need to know
  • Commitment shows in protected downtime and funding during lean periods, not in kickoff speeches.
  • Senior leaders set the ceiling for strategy selection and skill investment, so weak support caps everything downstream.
  • Constancy matters more than size: a modest program sustained for years beats a large one abandoned after two quarters.
Master this◆ Paid

The deep drill-down: 8 operational steps, a worked example from the source, 5 decision rules, 5 failure modes, and the “Executive Constancy Brief” tool. Included when you buy this guide.

The rest of this section

the full written section · 3 how-to steps · 2 pitfalls to watch for · 3 tools for this section. Included when you buy this guide.

Grounded in: Managing Factory Maintenance

Proactive Maintenance Strategy Selection
strong · 1 source
  • Managing Factory Maintenance
In this section

This section explains how to match PM, predictive maintenance, RCM, PMO, and TPM to each asset's failure consequences instead of applying one approach everywhere. The goal is to aim effort at the failures that are most dangerous, costly, or frequent.

Proactive Maintenance Strategy Selection

The extent to which the department deploys strategy fitted to consequences and life cycle—PM, predictive maintenance, RCM, PMO, TPM—rather than reactive bust-and-fix, targeting the most dangerous, expensive, or common failure modes.

Why it matters. A mismatched strategy either leaves critical assets running to failure or buries the crew in low-value tasks, and in both cases reliability gains fail to appear.

Myth

More preventive maintenance on every asset means better reliability, so the strategy is simply to maximize PM coverage.

Reality

Many failure modes are random and not age-related, so calendar PM does nothing for them and can introduce faults through intrusive work. The right strategy depends on consequence and failure pattern: condition monitoring for some assets, redesign for others, and run-to-failure for cheap, non-critical ones.

Tools for this
The least you need to know
  • Choose maintenance tactics by failure consequence and pattern, not by what is fashionable or what the budget happens to allow.
  • Run-to-failure is a legitimate strategy for low-consequence assets when chosen deliberately.
  • Prune PM tasks that no failure mode justifies; fewer, targeted tasks raise reliability and free labor.
Master this◆ Paid

The deep drill-down: 8 operational steps, a worked example from the source, 5 decision rules, 5 failure modes, and the “Failure-Mode Strategy Selection Sheet” tool. Included when you buy this guide.

The rest of this section

the full written section · 4 how-to steps · 2 pitfalls to watch for · 9 tools for this section. Included when you buy this guide.

Grounded in: Managing Factory Maintenance

Planning and Scheduling Discipline
strong · 1 source
  • Managing Factory Maintenance
In this section

This section separates planning (what the job requires) from scheduling (when it fits with production) and shows how each is run as its own discipline. Together they ensure people, parts, tools, and the asset arrive at the same time.

Planning and Scheduling Discipline

The maturity of distinct planning (resource identification, estimating, job packages) and scheduling (coordination with production, weekly schedules, backlog management) practices that converge people, parts, tools, and assets on time.

Why it matters. Without planning and scheduling, technicians spend much of their day hunting for parts, permits, and access, which inflates labor cost and drags down job quality.

Myth

Planning and scheduling are the same job, so a supervisor can handle both alongside running the crew.

Reality

Planning is advance preparation of job packages with parts, tools, and estimates; scheduling commits those jobs to a time agreed with production. Supervisors pulled into daily firefighting never get to either, which is why dedicated planners are needed.

Tools for this
The least you need to know
  • Planning prepares the job and scheduling commits it to a time; you need both, and neither can be absorbed into daily supervision.
  • Ready backlog measured in weeks of work shows whether the crew is keeping up or drowning.
  • A protected weekly schedule is the main lever for converting wasted waiting time into productive wrench time.
Master this◆ Paid

The deep drill-down: 8 operational steps, a worked example from the source, 5 decision rules, 5 failure modes, and the “Weekly Plan-to-Schedule Readiness Check” tool. Included when you buy this guide.

The rest of this section

the full written section · 4 how-to steps · 2 pitfalls to watch for · 4 tools for this section. Included when you buy this guide.

Grounded in: Managing Factory Maintenance

Maintenance Information Quality (Work Order/CMMS Integrity)
strong · 1 source
  • Managing Factory Maintenance
In this section

This section covers what makes work-order and CMMS data trustworthy enough to support analysis, benchmarking, and decisions. It focuses on capture habits rather than software features.

Maintenance Information Quality (Work Order/CMMS Integrity)

The completeness, accuracy, and consistency of data captured through work orders and the CMMS, forming the unique history used for analysis, benchmarking, and decision-making.

Why it matters. If failure histories are incomplete or miscoded, every analysis built on them points effort at the wrong assets and the reliability program rests on guesses.

Myth

Buying or upgrading a CMMS gives you reliable maintenance information.

Reality

The system only stores what technicians and planners enter, so data quality is a behavior and standards problem. A new CMMS filled with vague 'repaired pump' entries and inconsistent failure codes simply preserves poor information at higher cost.

Tools for this
The least you need to know
  • Data quality comes from disciplined capture on each work order, not from the software purchase.
  • A small, consistent code set beats a detailed one that nobody uses properly.
  • Show technicians the analyses their entries produce; people record accurately when they see the data change decisions.
Master this◆ Paid

The deep drill-down: 8 operational steps, a worked example from the source, 5 decision rules, 5 failure modes, and the “Work Order Record Audit Sheet (header and body)” tool. Included when you buy this guide.

The rest of this section

the full written section · 4 how-to steps · 2 pitfalls to watch for · 6 tools for this section. Included when you buy this guide.

Grounded in: Managing Factory Maintenance

Training, Cross-Training, and Skill Level
strong · 1 source
  • Managing Factory Maintenance
In this section

This section describes how to invest in craft, multi-craft, and management training so workforce skills keep pace with modern equipment. It sets a benchmark of 1-5% of direct hours.

Training, Cross-Training, and Skill Level

The investment in continual craft, multi-craft, and management training that closes the gap between modern equipment technology and workforce skills, targeting 1-5% of direct hours.

Why it matters. Technicians without the skills to diagnose and repair modern equipment cause rework and induced failures, and no strategy or process can compensate for that.

Myth

Training is a discretionary expense that can be postponed in a busy year because experienced technicians learn on the job.

Reality

Experience on legacy machines does not transfer to controls, drives, and condition-monitoring tools that older staff never met. Deferring training widens the gap between equipment technology and workforce skill, and the cost reappears as longer repairs and repeat failures.

Tools for this
The least you need to know
  • The skills gap grows with every new machine generation unless training time is protected.
  • Target training at the equipment you actually run and the failures you actually have.
  • Cross-training pays when it shortens handoffs, and it also builds the ownership that sustains motivation.
Master this◆ Paid

The deep drill-down: 8 operational steps, a worked example from the source, 5 decision rules, 5 failure modes, and the “Training and Cross-Training Plan (per person)” tool. Included when you buy this guide.

The rest of this section

the full written section · 4 how-to steps · 2 pitfalls to watch for · 5 tools for this section. Included when you buy this guide.

Grounded in: Managing Factory Maintenance

Movement III · The run-it-now depth

The Playbook

Practical tools and examples from this guide.

Frameworks

Frameworkfree

Equipment Reliability (MTBF)

How this mechanism is run, step by step, as the literature describes it.

  1. 1Pick the assets first. Reliability work is directed at failure modes with the worst consequences (the RCM logic). Rank assets by what a breakdown costs in safety, downtime, damage and repair. Deliberately park low-consequence equipment as BNF (Bust 'N Fix, no PM) so effort goes where it pays.
  2. 2Identify each asset's life cycle stage: start-up, wealth or breakdown. The PM strategy differs by stage, so do not apply one standard task list to everything.
  3. 3Set the baseline from work-order history. For each critical asset, record breakdown events, the reason for repair, and the reason for write-up. Use these to calculate MTBF (reliability) and MTTR (cost of a typical failure). Count call backs and rework as failures of the original job, not as new, unrelated events.
  4. 4Place the asset on the A/B/C curve. Curve A is life with little attention, set by design, build and operating conditions. Curve B is the longer life PM and predictive maintenance buy: cleaning, keeping everything tight, correct lubrication. Curve C is life that is longer even when left unattended. Write down which curve each asset sits on and what spend holds it there.
  5. 5Build the PM and PdM task list to hit the failure mode. Choose the PM clock (days, pieces, machine hours or cycles) that matches how the asset is used. Add predictive inspection (vibration, oil analysis, infrared) where it can flag a failure before it occurs. Set starting frequencies, then adjust them with the failure data.
  6. 6Use MTBF to schedule Planned Component Replacement (PCR). Replace components on a schedule based on MTBF, downtime costs and other factors, instead of waiting for the breakdown.
  7. 7For every repeat failure, do root cause analysis and design a repair that prevents it (maintainability improvement). The aim is Curve C: more MTBF without pouring money in every month. First estimate the cost of the fix against the cost of the problem. Do not spend $50,000 to avoid a $100 problem.
  8. 8Track MTBF and MTTR per asset on a fixed cycle. Protect the PM budget while you do. A cut to PM does not show up in the failure rate until the curve has decayed back to A, so a flat month after a cut is not evidence the cut was safe.
Framework◆ Paid

Maintenance Information Quality (Work Order/CMMS Integrity)

How this mechanism is run, step by step, as the literature describes it.

◆ The full 8-step framework — included with this guide purchase

Framework◆ Paid

Organizational Competitiveness and Survival

How this mechanism is run, step by step, as the literature describes it.

◆ The full 8-step framework — included with this guide purchase

Framework◆ Paid

Planning and Scheduling Discipline

How this mechanism is run, step by step, as the literature describes it.

◆ The full 8-step framework — included with this guide purchase

Framework◆ Paid

Plant Availability and Output (OEE)

How this mechanism is run, step by step, as the literature describes it.

◆ The full 8-step framework — included with this guide purchase

Framework◆ Paid

Proactive Discipline and Attitude

How this mechanism is run, step by step, as the literature describes it.

◆ The full 8-step framework — included with this guide purchase

Framework◆ Paid

Proactive Maintenance Strategy Selection

How this mechanism is run, step by step, as the literature describes it.

◆ The full 8-step framework — included with this guide purchase

Framework◆ Paid

Maintenance Process Quality

How this mechanism is run, step by step, as the literature describes it.

◆ The full 7-step framework — included with this guide purchase

Framework◆ Paid

Top Management Support and Constancy of Purpose

How this mechanism is run, step by step, as the literature describes it.

◆ The full 8-step framework — included with this guide purchase

Framework◆ Paid

Total Cost of Maintenance

How this mechanism is run, step by step, as the literature describes it.

◆ The full 8-step framework — included with this guide purchase

Framework◆ Paid

Training, Cross-Training, and Skill Level

How this mechanism is run, step by step, as the literature describes it.

◆ The full 8-step framework — included with this guide purchase

Framework◆ Paid

Worker/Operator Ownership and Motivation

How this mechanism is run, step by step, as the literature describes it.

◆ The full 8-step framework — included with this guide purchase

Checklists

Checklistfree

Equipment Reliability (MTBF) — decision rules

  • If an asset's failure has severe safety, damage or downtime consequences, then put PM, PdM and redesign effort there first. If consequences are minor and PM does not pay, then leave it as BNF on purpose.
  • If MTBF holds only while PM money keeps flowing (Curve B), then keep the PM funded and look for a redesign that moves the asset toward Curve C.
  • If a job produces call backs or rework, then count it as a reliability failure and investigate the materials, skills or scope of the original job before adding PM.
  • If a failure repeats, then do root cause analysis instead of repeating the repair. Like snaking a drain every month without removing the hardened buildup, repeating the repair treats the symptom.
  • If a proposed improvement costs more than the failures it prevents, then do not do it. Test it against the cost of the problem first.
Checklist◆ Paid

Maintenance Information Quality (Work Order/CMMS Integrity) — decision rules

◆ All 5 checkpoints — included with this guide purchase

Checklist◆ Paid

Organizational Competitiveness and Survival — decision rules

◆ All 5 checkpoints — included with this guide purchase

Checklist◆ Paid

Planning and Scheduling Discipline — decision rules

◆ All 5 checkpoints — included with this guide purchase

Checklist◆ Paid

Plant Availability and Output (OEE) — decision rules

◆ All 5 checkpoints — included with this guide purchase

Checklist◆ Paid

Proactive Discipline and Attitude — decision rules

◆ All 5 checkpoints — included with this guide purchase

Checklist◆ Paid

Proactive Maintenance Strategy Selection — decision rules

◆ All 5 checkpoints — included with this guide purchase

Checklist◆ Paid

Maintenance Process Quality — decision rules

◆ All 5 checkpoints — included with this guide purchase

Checklist◆ Paid

Top Management Support and Constancy of Purpose — decision rules

◆ All 5 checkpoints — included with this guide purchase

Checklist◆ Paid

Total Cost of Maintenance — decision rules

◆ All 5 checkpoints — included with this guide purchase

Checklist◆ Paid

Training, Cross-Training, and Skill Level — decision rules

◆ All 5 checkpoints — included with this guide purchase

Checklist◆ Paid

Worker/Operator Ownership and Motivation — decision rules

◆ All 5 checkpoints — included with this guide purchase

Case studies — including what didn't work

Case studyfree

Equipment Reliability (MTBF)

Context

The source's cylinder example shows the mechanism. An asset with cylinders left alone follows Curve A: its MTBF is set by how it is used, how well it is engineered and built, and the conditions it runs in. Cleaning the cylinders, keeping everything tight and adding the right amount of lubrication shifts the life curve to the right (Curve B), giving a longer average life. That shift lasts only while PM labor and materials keep flowing. If a new manager cuts PM to look good, nothing happens to the failure rate until enough time passes for the curve to decay back to A. Profit rises in the short term, and the next manager inherits the breakdowns. The durable fix is Curve C: better seal kits, better cylinders and better protection, so the unattended life exceeds both A and B. To use this, record the cylinder's failures before PM, after PM, and after the redesign. Then check whether the MTBF gain survives without added monthly spend. The test is that the improvement must cost less than the failures it removes.

Case study◆ Paid

Maintenance Information Quality (Work Order/CMMS Integrity)

Context

The passages give no numeric case, so this one is constructed from the book's own definitions and is illustrative only. The book's improvement discussion tracks the average life (MTBF) of a component such as an air cylinder across maintenance strategies. Suppose you want that figure for a cylinder on one packaging machine. You pull the work orders. Three are written against 'Line 4' rather than the unit, one has a blank body, and two have free-text reasons ('leaking', 'bad'). You score the header audit: the unit field is wrong on three of six orders. The body audit: one order is empty. The result is that only two of the six orders can be used for MTBF. You then add a required unit field tied to the asset master file, a reason-for-repair pick list, and a closure rule that blocks a job with an empty body. After the next quarter you re-audit, and every cylinder failure can be placed on the right unit with a consistent reason. At that point the MTBF comparison between 'bust-and-fix' and PM becomes defensible.

◆ What happened, and the outcome — included with this guide purchase

Case study◆ Paid

Organizational Competitiveness and Survival

Context

A Maryland plastics extruder had a maintenance worker use a new vibration analysis tool and find a problem in the gear driving the main extruder screw. Repairing it immediately cost $500; after breakdown the bill would jump to $5000, so he claimed a $4500 saving and was proud of it. He took the plan to the shift manager, and the passage warns that a good maintenance decision can still work against the organization when maintenance lacks production and financial data, such as the cost of downtime at the moment of repair. The lesson is that competitiveness is measured at the level of unit cost and availability, not repair cost alone. Before scheduling the repair, price the stoppage against production and schedule it where it costs the plant least. The $4500 figure covers only repair cost and ignores that timing.

◆ What happened, and the outcome — included with this guide purchase

Case study◆ Paid

Planning and Scheduling Discipline

Context

At a Maryland plastics extruder, a maintenance worker used a new vibration analysis tool and found a problem in the gear driving the main extruder screw. Fixing it now would cost $500. After a breakdown, the bill would be $5,000, so he claimed a $4,500 saving. He and the maintenance manager agreed with the shift manager to repair it on 2nd shift. The repair took unit 5 off line for a shift and a half. At Wednesday's production/maintenance scheduling meeting the manager met a chilly silence: production had missed a just-in-time delivery to a new customer, putting almost $40,000,000 of new business at risk. The planning was sound: the problem was found early, the repair was identified and the cost was estimated. The scheduling was the failure. The decision was never run through production, the master production schedule was never checked, and the weekly schedule was never signed off by operations. Applying this construct, the repair would have been planned with a job package and estimate. It would then have been slotted into a window agreed with production, with the delivery commitment visible, and the $4,500 'saving' would have been tested against what the downtime cost.

◆ What happened, and the outcome — included with this guide purchase

Case study◆ Paid

Plant Availability and Output (OEE)

Context

The source gives two anchors. First, the utility example: a Midwest generating station was designed for 85-95% availability. To support that, designers met with maintenance leadership and discussed every failure mode, planned for it, and designed it out where possible. The capital spares inventory was $24 million, since reduced by maintenance to $15 million. Availability was treated as a design target tied to maintenance input, not an afterthought. Second, the source's general OEE range: a typical factory runs 50-80% OEE, and most could add 10-25% output by recovering about half the waste. Illustration (the 60% figure is hypothetical, not from the source): a line scores 60% OEE, so 40 points are wasted. You log the 40 points to breakdowns, model changes, material problems, and small jam-ups. Recovering half of that waste, 20 points, takes the line to 80%, with no new machines. You then work the largest-loss categories first and report the result as added output, which is the language management uses.

◆ What happened, and the outcome — included with this guide purchase

Case study◆ Paid

Proactive Discipline and Attitude

Context

The source's sewer-line case shows the difference between firefighting and root cause. A crew snakes out an old cast or galvanized sewer line every month and is never confident it will stay open. A parts changer keeps scheduling the next snaking. A proactive mechanic studies the slow drainage and finds the root cause: hardened buildup inside the pipes. The analysis also estimates the cost of leaving the defective pipe in place, so the decision between continued snaking and replacement rests on numbers. The source adds that some problems should not be fixed, so the cost estimate decides, not reflex. The same logic applies to a crew moving from reactive to PM work. Many emergencies persist at first because of unfunded maintenance liabilities, so the proactive discipline is to keep the PM work going while funding the backlog separately.

◆ What happened, and the outcome — included with this guide purchase

Case study◆ Paid

Proactive Maintenance Strategy Selection

Context

The source describes a utility that holds detailed meetings with maintenance leadership. Every failure mode is discussed, looked at, planned for, and, where possible, designed out. The utility treats profit in power generation as depending on maintenance input to design and operation. In this case the capital spares inventory was $24 million, and maintenance has just reduced it to $15 million. That outcome follows from strategy fitted to consequence: modes are understood and planned for, so spares are bought for known risks rather than as general insurance. A smaller example from the source's glossary shows the same logic at pipe scale. A crew snakes an old cast or galvanized sewer line every month, which is reactive work repeated forever. The root cause analysis finds hardened buildup inside the pipe. The study estimates the cost of leaving the pipe in place against the cost of replacing it, and the decision follows the numbers. In both cases the action is chosen after the failure mode and its consequence are understood.

◆ What happened, and the outcome — included with this guide purchase

Case study◆ Paid

Maintenance Process Quality

Context

Take an air cylinder analyzed across the three strategies in the passages. Under 'bust'n'fix' each cylinder deteriorates and fails at its own point, and with many cylinders the failures spread into a bell-shaped distribution — the whole area under the curve is the whole population, and eventually they all break. PM shifts that distribution by intervening before failure, extending average MTBF. Permanent maintenance improvement (re-engineering the component or its application) shifts it further still and is why re-engineering and maintenance improvements account for 39% of continuous-improvement dollars in the passage's breakdown. The process-quality point is that you don't pick PM because it feels proactive; you pick the strategy that fits the component's failure distribution — 'strategies must fit the circumstances.' Building the PM task list, the planned package, and the completion feedback around that distribution is what makes the result repeatable instead of heroic.

◆ What happened, and the outcome — included with this guide purchase

Case study◆ Paid

Top Management Support and Constancy of Purpose

Context

A power utility builds a generating station in the Midwest with a design specification of 85-95% availability. To support it, the designers hold long, detailed meetings with the maintenance leadership. Every failure mode is discussed, looked at, planned for, and where possible designed out. The capital spares inventory is $24 million, which the maintenance department has just reduced to $15 million. Management funds a large spares position because it understands that profit in power generation depends on maintenance input to the design and operation of the plant. Maintenance is consulted at design time, trusted with a large inventory, and credited when it trims that inventory. That is top-management understanding, funding, and constancy of purpose in practice. Use it as the model: seek the design-stage seat, bring failure-mode detail, and show the dollar link between spares and downtime.

◆ What happened, and the outcome — included with this guide purchase

Case study◆ Paid

Total Cost of Maintenance

Context

The source gives no dollar figures for the cost curve, so this example uses its OEE numbers to show the Stream B side. A typical factory has an OEE of 50% to 80%, so 20% to 50% of potential output is wasted on breakdowns, model changes, material problems, and small jam-ups. Take a plant at 60% OEE (an illustrative pick inside the stated range), which wastes 40%. The source says most plants could recover about half of the waste without spending on expansion, which is about 20 points of output here, or 10% to 25% across the stated range. That recovered output is the value of lower downtime, which sits on the breakdown side of the cost curve. Next, price one recurring failure: MTTR times the labor and parts rate, plus lost production, multiplied by its MTBF-based frequency. Compare that figure with the PM hours and PM-caused interruptions spent trying to prevent it. If added PM hours cost less than the breakdown cost they remove, you are on the under-PM side of the balance. If added hours stop removing failures, you have passed the minimum.

◆ What happened, and the outcome — included with this guide purchase

Case study◆ Paid

Training, Cross-Training, and Skill Level

Context

The book's refinery mothball case shows what an undistributed maintenance knowledge base costs. When oil prices fell, a company decided to mothball a refinery. Accounting estimated savings of $10 to $15 million per year and a restart cost of $75 to $100 million. To maximize the savings, they laid off the entire maintenance staff and left only security on site. After 8 years, oil prices recovered and the company wanted the refinery back online for large contracts. Because of a lack of basic maintenance knowledge and of effective communication, the refinery was almost a complete loss and cost almost $700 million to bring back into service. Maintenance knowledge would have shown that $2 to $3 million per year preserved the plant, or $16 to $24 million over the 8 years. The same gap exists inside a running plant, just smaller: finance and other departments decide without maintenance knowledge, and maintenance people lack current technical skills. Spreading that knowledge through cross-department teams and structured training is the investment the 1-5% hours target pays for.

◆ What happened, and the outcome — included with this guide purchase

Case study◆ Paid

Worker/Operator Ownership and Motivation

Context

A blending-system call shows why wide request access needs training. A work request described a broken main computer. The technician took the description at face value and was misled for several hours. The system was acting exactly as designed. The second product's pump was not activating because the source tank for the first product was empty, and the gauging system also looked out of range. The source's point is that good requests carry only the observable, not the inferred. Applied here, the requester should write what the display and pumps were doing, not a diagnosis of the computer. The ownership move is not to take request-writing away from operators. Keep access wide, because it makes people feel part of the operation, and run the mini-course so each request is something a technician can act on. The same logic covers PM handover. The trucker's pre-trip inspection is the model: operators do part of the checking, but only against a defined task, and it is required by law in trucking and aviation.

◆ What happened, and the outcome — included with this guide purchase

Templates

Templatefree

Asset Reliability Curve Tracker

Template◆ Paid

Work Order Record Audit Sheet (header and body)

◆ The fillable template — included with this guide purchase

Template◆ Paid

Competitive Position Scorecard (maintenance to survival)

◆ The fillable template — included with this guide purchase

Template◆ Paid

Weekly Plan-to-Schedule Readiness Check

◆ The fillable template — included with this guide purchase

Template◆ Paid

OEE Loss Ledger (per machine or area)

◆ The fillable template — included with this guide purchase

Template◆ Paid

Proactive Discipline and Root Cause Log

◆ The fillable template — included with this guide purchase

Template◆ Paid

Failure-Mode Strategy Selection Sheet

◆ The fillable template — included with this guide purchase

Template◆ Paid

Process-Before-Aid Readiness Sheet

◆ The fillable template — included with this guide purchase

Template◆ Paid

Executive Constancy Brief

◆ The fillable template — included with this guide purchase

Template◆ Paid

PM Balance Cost Worksheet (per asset or asset class)

◆ The fillable template — included with this guide purchase

Template◆ Paid

Training and Cross-Training Plan (per person)

◆ The fillable template — included with this guide purchase

Template◆ Paid

Asset Ownership Handover Sheet

◆ The fillable template — included with this guide purchase

Items marked Paid are included when you buy this guide.

Movement IV

Reflect

Consider the book's evidence, limitations and how it compares with other sources.

In this part

How good is it — where the book stands against the field, what it leaves open, and when to trust it.

  • — Its positioning, its critique, its blind spots
  • — When to apply it — and when not
  • — The evidence behind the advice

Book profile · in the corpus

This book’s model, against the corpus

12 of 12 constructs align with the field · 0 the book adds · 3 where it diverges · the field spans 35 constructs across 11 books

shared with the corpusthe corpus adds (other sources)where it diverges

Shared with the corpus — corroborated by other sources

Top Management Support and Constancy of PurposeProactive Maintenance Strategy SelectionPlanning and Scheduling DisciplineMaintenance Information Quality (Work Order/CMMS Integrity)Training, Cross-Training, and Skill LevelProactive Discipline and AttitudeWorker/Operator Ownership and MotivationMaintenance Process QualityEquipment Reliability (MTBF)Plant Availability and Output (OEE)Total Cost of MaintenanceOrganizational Competitiveness and Survival

Where it diverges — the book and the field pull apart

Proactive Maintenance Strategy SelectionPlanning and Scheduling DisciplineTraining, Cross-Training, and Skill Level

The corpus adds — from 10 other sources this book doesn't cover

The full field guide folds in ideas this book doesn’t reach — drawn from 10 further sources and cited in the full model.

This book’s place in the corpus

1 of 11
sources in this corpus
12
constructs contributed
12
corroborated by others

Why the corpus guide, not just this book

The book stands on the shared maintenance-management consensus (top-management support, planning, PM/RCM, reliability, OEE, cost, competitiveness) and is a practical authority on training investment levels, operator ownership and the proactive mindset. The reconciled field-guide still adds the human-error and safety-culture constructs, planner staffing, inventory and wrench-time measures, benchmarking, and error-management and defences, none of which the book covers.

This guide stands on the shoulders of this book and 10 other sources — every claim cited, the disagreements named.

Read the reconciled Maintenance Repair Leadership guide →

Read it closely

The book, examined

Not a summary — a close analytical reading: how the book is built, what it leaves open, and where it falls short.

How it’s built — the argument in order

  1. 01
    1. Framing: why maintenance matters now — Reframes maintenance from a 'necessary evil' cost center into a strategic asset. The case rests on globalized competition and the retirement of skilled workers. It argues the real payoff is plant availability, quality and output (OEE), not just lower maintenance cost, and asks what top management actually wants from maintenance.
  2. 02
    2. Evaluating current practices and the road from reactive to proactive — Gives the reader benchmarks and self-assessment tools to find where the department stands. Sets out the improvement cycle of commitment, measurement, information, investigation and action, and says improvement is everyone's job.
  3. 03
    3. Core maintenance processes: work orders, planning, scheduling — Treats the work order as the foundation of information. Separates planning from scheduling, with the rule that on larger jobs an hour of planning saves 3-5 hours of execution. Shows how work is identified, executed and captured for analysis.
  4. 04
    4. Computerization (CMMS) and organizational readiness — Argues that CMMS success depends on culture as much as software. Training starts before vendor selection, mechanics and supervisors are involved, and the vendor and customer share setup. It offers a ten-question readiness check covering management support, resources and stakeholder involvement.
  5. 05
    5. Choosing a deterioration strategy: PM, PdM, RCM, PMO, TPM, bust-and-fix — Argues that strategy must fit equipment consequences and life cycle. The excerpts show the PMO steps from policy determination (task economics against failure cost times probability), through grouping of tasks by group and skill, to approval, implementation and a 'living program'. They also show the PM argument: unfunded maintenance liabilities, the culture of reactive 'excitement junkies', and the need to fund past neglect separately.
  6. 06
    6. Detecting failure: the P-F curve and task frequency — Gives the technical logic for inspection and PdM. Points A to D mark who or what can detect a developing failure and how much lead time that gives. The rule is to inspect about twice as often as the detection-to-failure interval, and to drive PM intervals from unit-level usage measures.
  7. 07
    7. Integration with production, purchasing, stores and accounting — Treats maintenance as one function in a network of departments. It covers justifying, budgeting and staffing the effort, and the communication and approvals that cross department lines.
  8. 08
    8. People and management disciplines — Covers training, cross-training, supervision, communication, time management, and the cost of fear-driven layoffs. People are named the primary asset and the soft disciplines are tied to sustained performance.
  9. 09
    9. Synthesis and ultimate goal — Pulls the tools, formulas, task lists and references into one story. It ends on the aim that maintenance should reduce and eventually eliminate the need for maintenance.

What it leaves unsolved

How much historical underinvestment can an organization realistically repay, and over what time frame, before PM starts to show returns?

The unfunded-liability passage says the 'only way through' is to 'pay the piper' and rebuild, and that a separate budget line is needed. It gives no sizing method, payback profile or way to tell how many hidden failures exist, so the pitch to top management stays qualitative.

How can a plant change a reactive culture whose crews enjoy the excitement of breakdowns?

The 'excitement junkies' point is named as the harder cultural problem. The text says the organization 'has to decide what kind of shop floor it really wants' and that results come 'after a few years of consistency', but it offers no concrete method for changing motivation or incentives.

How do you actually estimate the probability and cost of failure that PMO's task-level microeconomics depend on?

PMO asks whether labor and materials times frequency is worth the cost of failure times its probability. Plants with weak data, the very ones the book says need help, may not have those numbers, and the excerpts do not say how to estimate them.

How can the P-F interval be set when point D (the true start of failure) cannot be detected and the detectable points vary by asset and technique?

The curve admits that D 'cannot be detected with existing technology' and calls it only a theoretical maximum. How to find practical A, B and C values for a specific failure mode is left to judgment, and the 'twice as often' rule is a heuristic with no stated error margin.

Can maintenance really be reduced toward elimination, and what are the practical limits?

The ultimate goal is stated as eliminating the need for maintenance, yet the strategies described depend on continued inspection, PM and rebuilds. The book does not say where reduction stops or what design and operating changes make it possible.

How should the implementation burden of a CMMS be balanced against the call to involve every level and keep top-management support through 'inevitable ups and downs'?

The ten-question check asks whether there is 'enough time, money, and interest', but the excerpts do not say what to do when the answer is no, or how to stage a smaller start.

How does the approach hold up as skilled workers retire and global production shifts, which the book names as the stakes?

The framing makes the retirement of skilled staff a reason for urgency, but the excerpted methods (training, cross-training, communication) do not show how knowledge is captured and transferred at the scale of the problem.

Where it falls short — a fair critique

incomplete

The P-F rule that tasks be done about twice as often as the detection-to-failure interval, or at 1/2 (C-A), is given with no evidence or discussion of variability. Real intervals are uncertain, and one inspection landing in the window does not guarantee a catch. The treatment is also unclear in places: the point labels and the 'A to C' window are hard to follow without the figure.

incomplete

The unfunded-liability argument assumes most failures are wear processes with a 'tail in the past and a failure in the future'. It does not address random, early-life or externally caused failures that no inspection would predict, and it asserts 'hundreds or possibly thousands' of such items without data. This overstates how much PM and PdM can find.

illogical

The 90% rule attributed to the software vendor (no more than 90% of setup done by either party, so expertise is 'commingled') is an arbitrary figure. It comes from an interested party and is offered as a rule of thumb with no rationale. It also sits uneasily beside the advice to have supervisors and lead mechanics do much of the data research.

incomplete

The 'excitement junkies' diagnosis puts a systemic problem on crew temperament. It does not consider the incentives, staffing, parts availability or management rewards that sustain reactive firefighting. The cure offered is time and consistency, with no tools for changing those structures.

incomplete

The PMO microeconomic test (task cost against failure cost times probability) is narrowly financial in the excerpt. It gives limited guidance on safety, environmental or regulatory consequences that cannot be traded off against cost, and on the uncertainty of the inputs. The consequence step before it hints at this but the excerpt does not develop it.

uninformed

The claims that proactive maintenance raises OEE and competitiveness, and that PM and PdM are 'widely separated' in the literature, rest on the author's teaching experience and anecdote. The excerpts cite no comparative studies or datasets, so the causal chain from maintenance practice to plant output and survival is asserted rather than demonstrated.

uninformed

The CMMS discussion is framed around selecting a vendor package, involving 'data processing management' teams, and building master files by hand. That reads as an older IT-era model, and the excerpts do not address newer data sources such as sensor-fed condition monitoring or analytics, which bear on the book's emphasis on information quality and PdM.

incomplete

The book tries to cover strategy, process, computerization, finance, integration and people in one reference. In the excerpts this breadth shows as brief, checklist-style treatment of hard trade-offs, such as how to sequence PM, PdM, RCM, PMO and TPM when resources are limited. Only the lists of steps and questions are given.

Before you apply it

Using it well

Where the method fits, who it’s for, and the honest case for and against — so you apply it where it works.

Is this book for you?

For you if

  • You are a maintenance supervisor, manager or planner who wants a coherent reference covering processes, tools and people issues
  • You run a largely reactive maintenance operation and want a path to proactive practice
  • You must justify, computerize, budget or staff a maintenance effort and need to make the case to top management
  • You want to link maintenance to plant output, quality and competitiveness, not just repair speed

Skip it if

  • You need deep engineering or statistical detail on one technique such as vibration analysis or full RCM, since this is a broad field guide
  • You are a top executive wanting only a short strategic summary and not operational how-to
  • Your operation is not a factory or plant with significant equipment (the guidance is manufacturing-centered)

Need first

  • Basic familiarity with maintenance terms (PM, PdM, work orders, MTBF, OEE)
  • An honest assessment of your current practices and where the department stands
  • Some level of management support and willingness to fund training and past-neglect catch-up
  • Access to or willingness to build basic work order and equipment data

When it applies — and when it doesn’t

Use it
  • A plant stuck in constant firefighting, with a backlog of deferred repairs and rising breakdowns — the book frames this as 'unfunded maintenance liabilities' and prescribes PM/PdM plus a separate budget line to bring assets up to standard
  • Selecting and rolling out a CMMS across the maintenance department — it gives a concrete approach: involve mechanics and supervisors early, train before selection, secure management support, and ask ten readiness questions
  • Existing PM program that is bloated, duplicative or of unclear value, and you want to rationalize it — PMO's task-by-task economics (cost of task vs. cost of failure x probability) and grouping steps target exactly this
  • Setting inspection or PdM frequencies for equipment with a detectable warning period before failure — the P-F curve logic (inspect at about half the warning interval) gives a clear rule for choosing frequency
  • Large, complex jobs such as shutdowns or major rebuilds — the planning rule of thumb says an hour of planning saves 3-5 hours of execution, and planning is kept distinct from scheduling
Adapt it
  • Buying CMMS software while staff are unprepared and management commitment is thin — the book warns that without cultural readiness and sustained support the system gets only superficial acceptance
  • Expecting quick, visible results from a new PM or PMO program — the book says emergencies persist for months and a living program takes years of consistency as freed resources are reinvested
  • Culture where crews thrive on the excitement and autonomy of reactive work — the 'excitement junkies' problem is cultural and harder to change than the technical one, so expect resistance
  • Using detailed analysis and optimization on poor work order or equipment data — all analysis and decisions rest on good information centered on the work order, so fix data capture first
Not here
  • Applying one uniform strategy (all PM, or all predictive) to every asset — the thesis is that strategy must match each asset's failure consequences and life cycle, including bust-and-fix where cheap
  • Justifying maintenance purely as a cost-cutting exercise — the book argues the real payoff is OEE and plant output, so a cost-only frame misses the point and undermines support
  • Cutting maintenance staff through fear-driven layoffs to hit short-term budgets — the book treats people as the primary asset, and fear-driven layoffs erode training and the performance that sustains improvement

The honest case

Strongest case for

  • Maintenance affects availability, quality and output, so treating it as a strategic lever rather than a cost center ties it directly to competitiveness and survival
  • Reactive maintenance accumulates unfunded liabilities, so deferring investment only worsens failures, and the book's remedy (PM/PdM plus clearing the backlog) addresses root causes
  • Matching strategy to consequence and life cycle (PM, PdM, RCM, PMO, TPM, bust-and-fix) is economically rational and avoids both over- and under-maintaining
  • Work-order-centered information gives a factual basis for analysis and improvement, and the planning-payoff ratio is concrete and actionable
  • Investing in people, cross-training and communication supports sustained improvement, especially as skilled workers retire

Strongest objection

  • The prescriptions assume long-term top-management constancy, patient investment and a sizable up-front catch-up budget that many plants cannot get
  • Breadth over depth: it covers many methods in one volume, so readers may get rules of thumb (such as 1-hour-to-3-5-hours planning savings) without evidence they hold in their setting
  • Heavy emphasis on PM, CMMS and process discipline can create bureaucracy and data burden, and some PM tasks may cause failures or add cost
  • The aim of eliminating the need for maintenance is aspirational and may be unrealistic for aging equipment or capital-constrained firms
  • Much of the evidence is the author's experience and anecdote from training, not controlled studies, so causal claims about output and competitiveness are not rigorously established
Source notes

The model's constructs are drawn from the source element(s); load-bearing constructs are corroborated across the shelf, emerging ones are flagged.

Ideas covered by the source notes

  • Top Management Support and Constancy of Purpose
  • Proactive Maintenance Strategy Selection
  • Planning and Scheduling Discipline
  • Maintenance Information Quality (Work Order/CMMS Integrity)
  • Training, Cross-Training, and Skill Level
  • Proactive Discipline and Attitude

Movement V

Measure

Use available assessments to reflect on what you have learned.

In this part

A way to gauge yourself against the book's model, and the instruments it gives you.

  • — A self-check built from the book
  • — Instruments and what you'd measure next

Learning curriculum

After this book, you can…

The book's learning objectives, classified by Bloom's taxonomy and ordered so each builds on the ones before it.

01Foundational — know & understand
  1. explain
    After this book you can explain why maintenance is a strategic asset rather than a necessary-evil cost center, and how it contributes to plant output (OEE), quality, and competitiveness.
    Check: Short essay or presentation in which the learner makes the case to top management for maintenance's contribution to availability, OEE, and survival, citing the book's argument.
02Working — apply
  1. construct
    After this book you can identify what top managers want from maintenance and build a business case that secures funding, downtime, and long-term commitment (constancy of purpose), including a separate budget line for unfunded maintenance liabilities.
    Check: Prepare a written proposal/pitch for a PM or CMMS initiative that includes benefits, costs, a past-sins catch-up budget, and a long-term timeline; evaluate against a rubric.
  2. apply
    After this book you can apply root cause analysis and continuous-improvement steps (commitment, measurement, information, investigation, action) to prevent recurrence of failures and move toward reducing the need for maintenance.
    Check: Analyze a recurring failure case from work order history, identify the root cause, and propose a permanent fix and a measure to confirm results.
  3. apply
    After this book you can distinguish planning from scheduling and apply planning discipline (estimating, resource identification, job packages) and scheduling coordinated with production to improve wrench time.
    Check: Given a larger job, develop a job package with estimates and materials, then build a weekly schedule coordinated with production; justify expected savings using the 1 hour planning to 3-5 hours of execution rule.
03Advanced — analyze & judge
  1. differentiate
    After this book you can differentiate the deterioration strategies (PM, PdM, RCM, PMO, TPM, bust-and-fix) and select the one that fits an asset's consequences of failure and life cycle.
    Check: Case-based exercise assigning a strategy to several assets with justification based on failure consequences, cost, and life-cycle stage.
  2. integrate
    After this book you can integrate maintenance with production, purchasing, stores, and accounting by breaking down interdepartmental barriers and focusing on internal and external customer service.
    Check: Given a scenario with cross-department conflicts, analyze root barriers and propose information-sharing and coordination mechanisms with customer-service measures.
04Mastery — synthesize & create
  1. evaluate
    After this book you can evaluate the current state of a maintenance department against internal, best-in-class, and best-in-world benchmarks and measures, and identify the gaps to close.
    Check: Given sample plant data, compute key metrics (e.g., MTBF, OEE components, cost ratios), compare them to benchmarks, and recommend improvement priorities.
  2. design
    After this book you can design a work-order-centered process (identify, plan, schedule, execute, record) that captures complete, accurate, and consistent history for analysis.
    Check: Produce a work flow and work order form with required data fields and coding standards; review sample records to find data-quality flaws and propose corrections.
  3. judge
    After this book you can evaluate individual PM tasks and frequencies economically by comparing annual task cost (labor and materials times frequency) with the cost and probability of the failure avoided, and use PMO-style review to eliminate, regroup, or re-time tasks.
    Check: Given a PM task list with costs and failure data, calculate task-to-failure cost ratios, decide to keep, change, or drop each task, and assign tasks to the right group (operators, night shift, craft).
  4. develop
    After this book you can plan a transition from a reactive to a proactive department, addressing the practical (backlog, funding, unfunded liabilities) and cultural (excitement-junkie) obstacles and sustaining the program as a living one.
    Check: Write a phased implementation plan with resource reinvestment, change-management steps, communication, and milestones; critique for realism.
  5. design
    After this book you can design people-focused practices (training and cross-training plans, operator involvement via TPM, communication, and avoiding fear-driven layoffs) that build skill, ownership, and motivation.
    Check: Develop a training and ownership plan including skills-gap analysis, operator-maintainer tasks, and communication approach; evaluate against criteria.
  6. justify
    After this book you can justify, select, and implement a CMMS by assessing organizational readiness, involving stakeholders at all levels, and answering the key control-structure and resource questions before choosing a system.
    Check: Complete a CMMS readiness checklist and selection/implementation plan covering stakeholder involvement, training, resources, and data setup responsibilities; defend the choices.
  7. assess
    After this book you can assess overall maintenance performance by linking practices to reliability (MTBF), OEE, total cost, and competitiveness, and set a balanced PM level that minimizes total cost.
    Check: Capstone case: analyze a plant's data, determine the PM/repair cost balance, forecast effects on MTBF, OEE and unit cost, and recommend a prioritized improvement program.

How to measure it

Turning each idea into a measure

For each construct: how to operationalize it, the observable signals to look for, and how well it holds up.

Top Management Support and Constancy of Purpose

Assessed through budget stability across quarters, existence and awareness of a real mission statement, inclusion of the maintenance manager in strategic planning, and willingness to grant downtime for PM.

Observable signals
  • Multi-year maintenance budget
  • Maintenance in strategic planning meetings
  • Downtime granted when requested
  • Stable resource allocation in bad times
Scale

Perceptual assessment via stakeholder interviews and archival budget stability review.

Holds up?

Aligns with book's first four world-class attributes and Deming point 1. · May vary with respondent role; triangulate perceptions with budget records.

Proactive Maintenance Strategy Selection

Measured via presence and quality of task lists, PM-to-total-hours ratio, use of RCM/PMO analyses, and alignment of tasks to dangerous/expensive/common failure modes.

Observable signals
  • Existence of engineered task lists
  • Documented failure-mode-based task selection
  • PM hours as share of total
  • Condition-based/predictive tasks in use
Scale

Mixed archival and perceptual; can be scored on maturity of strategy fit.

Holds up?

Grounded in Maintenance Strategies and PM/RCM/PMO/TPM chapters. · Requires consistent classification of work; audit needed.

Planning and Scheduling Discipline

Tracked via schedule compliance percentage, ready-backlog held at 2-4 weeks, planner-to-craft ratios, and share of work formally planned before execution.

Observable signals
  • Signed weekly work lists
  • Ready backlog size
  • Planned job packages
  • Schedule compliance trend
Scale

Largely archival with perceptual elements; percentages and ratios.

Holds up?

Consistent with the planning/scheduling chapter and Fitness Questionnaire section D. · Depends on accurate work-order timekeeping.

Maintenance Information Quality (Work Order/CMMS Integrity)

Audited via random samples of work orders for header/body completeness, accuracy, and consistent nomenclature; incidence of faked or garbage data.

Observable signals
  • Work order audit check sheets
  • Consistent repair descriptions
  • System edit validations
  • Data integrity officer processes
Scale

Archival audit; percentage of fields complete/accurate/consistent.

Holds up?

Directly derived from work order audit figures and CMMS integrity discussion. · Reliable if audits are systematic and periodic.

Training, Cross-Training, and Skill Level

Measured via training hours per person per year (target 1-5% of direct hours), competence grid completion, and needs-assessment outcomes.

Observable signals
  • Training hours logged
  • Competence grids
  • Job requirement and needs assessment forms
  • Number of crafts qualified per worker
Scale

Mixed archival (hours) and perceptual/testing (competence).

Holds up?

Grounded in Craft Training chapter and Deming points 6 and 13. · Testing must be valid and job-relevant per ADA guidance.

Proactive Discipline and Attitude

Inferred from PM verification results, reduced firefighting proportion, and demonstration of the six PM-inspector attributes.

Observable signals
  • PM verification success (loosened-bolt tests)
  • Ratio of proactive to reactive work
  • Corrective write-ups from inspections
  • Self-directed analysis tasks completed
Scale

Perceptual and behavioral; hard to measure directly, use proxies.

Holds up?

Consistent with PM inspector attributes and proactivity discussion. · Proxy-based; subject to observer judgment.

Worker/Operator Ownership and Motivation

Assessed via engagement surveys, autonomous maintenance participation rates, and morale indicators under TPM.

Observable signals
  • Operators performing basic PM
  • Voluntary problem reporting
  • Low turnover/absenteeism
  • Participation in improvement teams
Scale

Perceptual self-report plus behavioral participation metrics.

Holds up?

Grounded in TPM chapter and world-class attributes on people. · Self-report susceptible to social desirability.

Maintenance Process Quality

Measured via rework/callback rate (target <3%), incidence of iatrogenic failures, and first-time completion rates.

Observable signals
  • Rework/callback percentage
  • Iatrogenic failure counts
  • First-time-fix rate
  • Customer satisfaction survey results
Scale

Archival counts and rates; supplement with satisfaction surveys.

Holds up?

Derived from Quality Improvement chapter and Deming point 3. · Depends on consistent categorization of rework.

Equipment Reliability (MTBF)

Quantified via MTBF, breakdown frequency, and maintenance-caused downtime hours tracked over time.

Observable signals
  • Computed MTBF per component/class
  • Trend of breakdown events
  • Downtime reason tracking
  • P-F curve position
Scale

Archival time-series from CMMS.

Holds up?

Consistent with improvement curves and P-F curve concepts. · Only as good as underlying data integrity.

Plant Availability and Output (OEE)

Computed as availability x performance efficiency x quality rate, benchmarked against best-in-class (e.g., 80%).

Observable signals
  • OEE percentage
  • Run time vs ideal
  • Speed loss data
  • Defect/reject rates
Scale

Archival production data; requires accurate run-time and defect capture.

Holds up?

Directly from OEE and TPM effectiveness case study. · Requires disciplined data collection on stoppages and defects.

Total Cost of Maintenance

Tracked via total maintenance dollars, cost per unit shipped, and position on the total-cost-of-maintenance curve.

Observable signals
  • Maintenance budget vs revenue ratio
  • Cost per product shipped
  • Downtime cost by machine
  • PM vs breakdown cost balance
Scale

Archival financial data; non-monotonic relationship with PM level.

Holds up?

Grounded in Total Cost of Maintenance figure and budgeting chapter. · Some costs (soft/intangible) are hard to capture.

Organizational Competitiveness and Survival

Assessed via market share trends, unit production cost, and avoidance of outsourcing or plant closure.

Observable signals
  • Unit cost benchmarks
  • Market share changes
  • Customer retention
  • Continued in-house production
Scale

Archival business metrics; aggregation not meaningful across units.

Holds up?

Consistent with the book's ridge-trail survival thesis and quality equation. · Confounded by many non-maintenance factors (currency, labor rates).

Self-assessment

Where would you like to improve?

This is a structured self-diagnostic built from the model — a mirror for reflection, not a validated psychometric scale. For validated measurement, see the instruments below.

1 = Strongly Disagree · 7 = Strongly Agree

Capabilitythe practices and skills you deploy
  • We choose maintenance strategies such as preventive, predictive, or reliability-centered maintenance based on each asset's failure consequences and life cycle, rather than just fixing things when they break.
  • Our maintenance jobs are usually started without a prepared job package, and the weekly schedule is frequently abandoned because of urgent breakdowns.
  • Our work orders and CMMS records are complete, accurate, and consistent enough that we rely on them to analyze failures and make decisions.
  • Our maintenance technicians and managers receive ongoing technical and cross-craft training that keeps their skills in step with the technology of our equipment.
  • Our maintenance work is done through defined processes that ensure the right job is done on the right asset, in the right way, with the right materials.
Alignmentthe outcomes you steer toward
  • The time between failures on our critical equipment has been getting longer, and breakdowns have become fewer and less severe.
  • Our plant's overall equipment effectiveness is held back by frequent downtime, slow running speeds, or quality losses that trace back to equipment condition.
  • We manage our total maintenance cost, including labor, materials, and downtime losses, by balancing preventive work against breakdown repairs.
  • Our maintenance performance gives us lower unit costs, higher availability, and better quality than our competitors.
Motivationthe states you cultivate in others
  • Our inspectors and mechanics carry out their tasks diligently without close supervision and act to prevent failures before they occur.
  • Our operators and mechanics take real pride and personal responsibility in the condition of the equipment they work with.
Supportthe conditions you shape
  • Our senior leaders understand the value of maintenance and consistently provide the funding, resources, and downtime it needs over the long term.
0 of 12 answered

Proposed measures — starter instruments where no validated one was found

Top Management Support and Constancy of Purpose Index (Proposed)

proposed · not validated

Rated for your team or hiring process — not a personal self-check.

  1. Senior leaders approve a multi-year maintenance and reliability budget that is protected from mid-year cuts and tracked against plan.
  2. Production downtime for planned maintenance is written into the operating schedule and honored by senior leadership when output pressure rises.
  3. Senior leaders review reliability and maintenance performance indicators in a recurring management meeting and document the decisions and resources that follow.

Scale: 1–7 (Strongly Disagree → Strongly Agree), rated by an evaluator or the team. Average the items; treat ≤3 as a gap to close in the process.

Proactive Maintenance Strategy Selection Index (Proposed)

proposed · not validated

Rated for your team or hiring process — not a personal self-check.

  1. Each critical asset has a documented maintenance strategy (e.g., PM, predictive, RCM, or run-to-failure) that is justified by a failure-consequence and life-cycle analysis.
  2. Maintenance strategies are reviewed on a defined cycle and revised using failure history and condition-monitoring data.
  3. The share of maintenance hours spent on planned and condition-based work is measured and reported, and it exceeds the share spent on reactive work.

Scale: 1–7 (Strongly Disagree → Strongly Agree), rated by an evaluator or the team. Average the items; treat ≤3 as a gap to close in the process.

Planning and Scheduling Discipline Index (Proposed)

proposed · not validated

Rated for your team or hiring process — not a personal self-check.

  1. Planners prepare job packages with a defined scope, labor estimate, parts, and procedures before the work is placed on the schedule.
  2. A weekly schedule is agreed with production before the week begins, and schedule compliance is measured and reviewed.
  3. Planning is organizationally separate from execution, and planners hold backlog and estimate-accuracy data that they review regularly.

Scale: 1–7 (Strongly Disagree → Strongly Agree), rated by an evaluator or the team. Average the items; treat ≤3 as a gap to close in the process.

Sources

  • Managing Factory Maintenance — Joel Levitt · A practical field guide to transforming a reactive maintenance department into a proactive, world-class function that boosts plant output, reduces costs, and eventually shrinks the need for maintenance itself.

The cheat sheet

Everything, on one page

One key takeaway from each section, with links to read more.

Publication details

Consult the sources listed in this guide for further reading. Edition 1 · Updated 2026-10-03.

Explore related books and profiles in the library.

Take it with you

The main guide above is free to read. This purchase includes 44 additional tools and examples — 11 frameworks, 11 checklists, 11 case studies and 11 templates — plus the full sections and the ebook itself: an epub and a PDF covering all 12 sections. Every format, yours to keep — permanently, including every future update. When this guide is deepened, you get the new edition at no cost.

One payment. The main guide stays free to read.

Get one letter a month: the new guides worth your time, and where the books disagree.

One letter a month from Leading With Data, plus a short welcome. Your address is used for this letter only. Unsubscribe any time.